Wednesday, November 19, 2008

Certificates of Occupancy!!

The certificate of Occupancy for 916 Oakwood (the first house) was received on 11/18, and today we got the CO for the second house 914. So now, there is electricity and heat in 916. It has been rented, and the first members of the community will move in to their new home in early December. Welcome to Lisa and Marisa!
John, Patrick and Brent are hard at work building the fence's for 916 and 914.









Cool fences, huh?! Some shrubs and mulch will make the houses look great! I sure wish it were a bit warmer, but it looks like I'll be breaking through some frozen ground this weekend.

914 Oakwood is almost done as well. The power gets turned on tomorrow. All the flooring is in and looks great. Only some minor work and cleaning inside. I can't wait for the heat to be started up Friday AM! Thanks to ARS for a great job - Tim Halat, the construction manager is very responsive and has been great to work with.
The second members of the neighborhood will be moving in in mid December - Welcome to Scott & Amy!
Jeff is almost done the stairway in 910 Oakwood - we are busily working away to get this house done by mid December for the third new neighbors. Joe and Erin are really excited about their new home!
This is 908 Oakwood. Chris and his crew have jacked it up and dug new footers, which will hopefully get inspected and have concrete poured by Friday. It is amazing how construction methods have changed - these houses originally were built with very little in the way of underground foundations.



Norman is digging out to place new foundation concrete around the bottom of the chimney so it will be stable in the new house.




This is the view from inside 908. Before long, it will look quite different!


Monday, November 3, 2008

First one - almost done, closing in on # 2!


The first house (916) is almost done and is now listed on Craigslist for sale or rent. The house has passed the final HVAC and Plumbing Inspections, and will likely pass the electrical inspection tomorrow. I hope to have the Certificate of Occupancy by the end of the week, with landscaping to be done over the next two weeks.




There are a few small items to finish, and the house needs to be cleaned, but it it really looking nice.








Ready for appliances!







The second house, 914 is moving along right on schedule. It is sold, and scheduled to close at the end of November. The interior is painted, the flooring is almost all in, tile work in process, and the kitchen cabinets will be in tomorrow. The countertops will be poured Wednesday and hopefully installed by early next week.




HVAC finish work will be done this week, and so will the electrical finish work. The staircase looks great with the white paint against the dark bamboo floors the buyers selected. Very classy!

910 is moving along too. The drywall went in last week, and trim carpentry should be done shortly, then paint! The buyers are looking forward to their December finish date.
912 is waiting at this point. The trim carpentry is in, and it's ready to be painted as soon as there is a buyer ready to choose colors.

The first of the "last two" houses has been torn down to the basics and is ready to have the new foundation poured.
This house will be slightly larger than the rest. It is a more square footprint, and will get a full 2nd floor rather than the "camelback" the other houses got. The attic will also be finished. As amazing as it looks from this picture, this house will be have 4 bedrooms and 3.5 baths when done!